Summary
Council approved a $1.2 million change order to fix pressing mechanical, plumbing, lighting, and automation issues at the MRAC facility. While most agreed the work is essential, some council members expressed concern over using a change order instead of competitive bidding.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Last discussed Jul 28, 2026.
Impact analysis
Cost of $1,206,621 funded through CIP budget allocations and unspent phase contingency funds.
MRAC patrons and city maintenance staff.
Mentions & discussions (4)
City gets MRAC updates and approves $186,500 for an update to the drinking water master plan.
The MRAC will close briefly from Oct. 2 through Oct. 12 to complete relining for the outdoor leisure pool, as well as painting and sealing the locker rooms.
Moab City Council Roundup
The purchase will replace aging cardio and cable equipment, much of which has been in use for more than 15 years.
City approves $1.2 million in upgrades to MRAC
The approved work is intended to extend the life of the 15-year-old building by replacing aging mechanical systems before they fail.
Regular City Council Meeting — July 28, 2026
Council approved a $1.2 million change order to fix pressing mechanical, plumbing, lighting, and automation issues at the MRAC facility. While most agreed the work is essential, some council members expressed concern over using a change order instead of competitive bidding.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Moab City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.